Drilled rivet holes in upper cowl. Fit lower cowlAnd ready to drill rivet holes.
28 Apr 2023
5.5 hours
FWF
#April-2023
#wes-April-2023
Share
Fit upper cowl. Drilled hinge holes.
27 Apr 2023
5.5 hours
FWF
#April-2023
#wes-April-2023
Share
Continued cowling work.
26 Apr 2023
6 hours
Section 45
#April-2023
#wes-April-2023
Share
Continues cowling work.
23 Apr 2023
2.5 hours
Section 45
#April-2023
#wes-April-2023
Share
Finished cowl attach hinge and pins.
18 Apr 2023
3.5 hours
Section 45
#April-2023
#wes-April-2023
Share
Worked on cowl hinges and hung pins.
17 Apr 2023
2 hours
FWF
#April-2023
#wes-April-2023
Share
Worked on on cowl hinges and pins. Temporary installed spinner back plate.
14 Apr 2023
3 hours
FWF
#April-2023
#wes-April-2023
Share
Finished red cube install. Installed blast tubes. Started preheat wiring.
11 Apr 2023
2 hours
FWF
#April-2023
#wes-April-2023
#Me
Share
Finished snorkel. Started red cube installation.
8 Apr 2023
3 hours
FWF
#April-2023
#wes-April-2023
Share
Continued snorkel work. Rivet prop governor cable holder. Install prop governor.
4 Apr 2023
5.5 hours
FWF
#April-2023
#wes-April-2023
#Me